Industrial Press Relocation in a Furniture Factory

Intra-plant relocation of a ~6-tonne industrial press inside a working furniture factory — completed in 3 days over the holiday shutdown by a 4-person crew, with zero safety incidents.

Industrial Press Relocation in a Furniture Factory — 1
Industrial Press Relocation in a Furniture Factory — 2
Industrial Press Relocation in a Furniture Factory — 3
Industrial Press Relocation in a Furniture Factory — 4
Industrial Press Relocation in a Furniture Factory — 5
Industrial Press Relocation in a Furniture Factory — 6

At a glance

Client

Confidential — furniture manufacturer

Industry

Furniture manufacturing

Location

Poland

Service

Turnkey machine relocation

~6 t press · intra-plant move · 4 specialists · 3 days

The challenge

A ~6-tonne industrial press had to be moved to a new position inside the same production hall — together with its adjoining conveyors — without damaging the machine or disrupting the plant’s schedule.

  • Heavy, one-piece machine: relocate a ~6-tonne press as a whole, without breaking it into sub-assemblies.
  • Live production plant: the move had to fit a tight window without holding up operations.
  • Two relocations at once: the press was moved in parallel with a cartoning machine over the pre-holiday and holiday days.

Our approach

  1. 1

    Survey & plan

    On-site survey, load-path and lifting-point calculations, and a move schedule built around the holiday window.

  2. 2

    Engineering & rigging

    Rigging on heavy-duty skates fed by a forklift, with load distribution sized for the ~6-tonne mass.

  3. 3

    Dismantling

    Disconnecting and detaching the conveyors; the press itself was prepared to be moved whole, without breaking it into sub-assemblies.

  4. 4

    Marking

    Component- and connection-level marking so everything could be reassembled exactly.

  5. 5

    Logistics

    Movement on skates within the hall — no off-site transport required.

  6. 6

    Assembly

    Setting the press on its new position and reconnecting the conveyors per the markings.

  7. 7

    Commissioning

    Functional checks and return to production.

What made it unusual

The whole operation ran over the pre-holiday and holiday days and in parallel with a second machine relocation (a cartoning line) — two coordinated moves inside one tight window, so the plant lost virtually no working production time.

Results

3 days

Timeline

≈ none — done over the holiday shutdown

Production downtime

0 incidents

Safety

~6 t · moved whole · fully recommissioned

Machine

The press was relocated and back in production within 3 days, with zero incidents and virtually no impact on output — because the work was scheduled into the plant’s holiday shutdown.

NM Solutions completed the relocation at express speed, even during the holiday period. Professionalism and timeliness at the highest level.

Plant management (client), furniture manufacturing