Selected work

Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth

Dismantling, marking, packing and loading a double drum dryer with its periphery at a cheese plant — the main unit weighing ~9 t even when stripped down. With no way to bring a forklift to it, we took it down off a 1 m concrete plinth on four electric hoists and lifted it out through an opening in the roof.

Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 1
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 2
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 3
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 4
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 5
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 6
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 7
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 8
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 9
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 10
Dismantling a 9-Tonne Drum Dryer from a Concrete Plinth — 11

At a glance

Client

Confidential — cheese producer

Industry

Food processing / dairy

Location

Germany

Service

Dismantling, marking & load-out

~9 t main unit · off a 1 m plinth without a forklift · out through the roof · 60 t crane · 3 specialists · 7 days

The challenge

A double drum dryer line had to be dismantled, marked, packed and loaded — but the machine stood on concrete beams about a metre high that a forklift simply couldn't reach, and the main unit weighed ~9 t even disassembled.

  • The drum unit sat on ~1 m concrete beams with no forklift access to it.
  • The main unit weighs ~9 t even when taken apart.
  • Everything had to be precisely marked so the line could be re-assembled later.

Our approach

  1. 1

    Survey & plan

    Measurement, assessment of extraction routes and a dismantling scheme.

  2. 2

    Engineering & rigging

    Jacks, transport skates and four 2.5 t electric hoists to take the machine down off the concrete beams without a forklift.

  3. 3

    Dismantling

    Unit-by-unit teardown of the dryer (drums, SEW drive, frame, pipework), lowering the main unit off the plinth on hoists and reducing weight for the move.

  4. 4

    Marking & packing

    Marking of every unit and connection for later assembly, packed for transport.

  5. 5

    Load-out

    Moving the equipment to an opening section of the roof; lifted out by a 60 t crane straight onto a standard curtain-side trailer.

What made it unusual

The machine was taken off a ~1 m concrete plinth without a forklift — on four 2.5 t electric hoists — then passed out through an opening section of the roof by a 60 t crane directly onto the truck.

Results

7 days

Timeline

3 specialists

Crew

~9 t

Main unit

0 incidents

Safety

In 7 days a 3-person crew took the 9-tonne drum dryer off its concrete plinth without a forklift, brought it out through the roof and craned it onto the truck — without a single incident, and marked so re-assembly raised no questions.

NM Solutions handled a tricky job carefully and in an organised way: the equipment was dismantled and loaded with no damage and no delays, despite the difficult access. The marking was done so well that re-assembly raised no questions.

Client representative, dairy / cheese production

Need heavy equipment dismantled and removed from a hard-to-reach hall? We handle the rigging, marking and load-out — request a project estimate.

* Required fields

We respond to project inquiries within 24 business hours.